Gov. Greg Abbott on Sept. 21, 2026, directed the Texas Commission on Environmental Quality to pause the issuance of all permits related to data center projects until the Electric Reliability Council of Texas completes its review, according to the governor's letter to then Executive Director Kelly Keel and a same day Office of the Governor press release.
The Sept. 21 letter says the Public Utility Commission of Texas, ERCOT, and the Texas Water Development Board need information from audits of data centers in the interconnection process, including effects on grid reliability and on water resources needed by communities. It says no other state agency shall move forward with regulatory approvals related to data centers until that information is acquired. It directed TCEQ to provide a compliance update by Oct. 19, 2026.
TCEQ October Compliance Update
In an Oct. 19, 2026, letter to the governor, Interim Executive Director Steven Schar wrote that TCEQ had paused the issuance of all permits related to the construction or development of infrastructure directly supporting data centers. The letter says staff were screening pending applications for ones subject to the directive and, where possible, suspending claimed authorizations for data center activities that do not require the agency to affirmatively issue a permit. It also says TCEQ had met with TWDB, the PUC, and ERCOT so agency directives stayed aligned.
TCEQ's Air Permitting pages describe types of New Source Review and Title V authorizations. Separately, TCEQ's Construction General Permit (TXR150000) covers stormwater discharges from construction activities that disturb one or more acres and discharge to surface water in the state.
ERCOT November Update to the PUC
ERCOT on Nov. 4, 2026, filed a letter and presentation in PUC Project No. 59142 for the Nov. 5 open meeting. The presentation, titled "Data Center State and Community Impact RFI: Preliminary Summary," says ERCOT issued the RFI to 465 loads and that 433 of 465 loads (93%) submitted responses, covering about 177 gigawatts, or about 97%, of requested interconnection capacity.
The same presentation says all 245 Large Loads of 75 megawatts or greater responded. It says Large Loads represent about 94% of requested interconnection capacity (about 166 GW). It says respondents answered 83% of nearly 67,000 RFI questions, which ERCOT called sufficient for a statistically meaningful analysis for the final report. It says detailed analysis was underway and that ERCOT was targeting a published final report on Dec. 10, 2026.
ERCOT's public Data Center Impact RFI page says the governor's Aug. 3, 2026, letter directed the PUC and ERCOT to obtain information on public financial assistance and tax benefits, dependency on grid power and on-site generation, water sources and consumption, cooling technologies, noise, light, and traffic impacts, and ownership and controlling interests. The page says ERCOT intends to collaborate with the PUC on a report to be published on or before Dec. 10, 2026.
West Texas Share of Requested Capacity
The Nov. 5 presentation says requests span every ERCOT Load Zone and that West Texas represents the plurality, with 41% of capacity (73 GW). West Texas is one of The Bluebonnet Express coverage regions. The same RFI categories cover water use, cooling, power supply, and community impact measures that the Aug. 3 letter directed ERCOT and the PUC to collect.
The governor's Aug. 3, 2026, letter to the PUC and ERCOT asked for projected annual and peak water consumption and anticipated sources of water supply, cooling technology details, and measures to reduce impacts on neighboring property owners and communities, including noise mitigation, light controls, setbacks, traffic improvements, and emergency response coordination.
Earlier Timeline for a December Open Meeting
In filings earlier in Project 59142, including an Aug. 20, 2026, presentation, ERCOT listed Dec. 10 as the date to file the Community Impact Review Report and Dec. 17 as a Commission open meeting date on that timeline. The PUC calendar lists an open meeting for Dec. 17, 2026. ERCOT's Nov. 5 preliminary summary restates the Dec. 10 target for a published final report. It does not, in the slides reviewed for this story, restate a Dec. 17 discussion date specifically for that report.
Header photo: Server racks inside a data center. Photo by PiDatacenters, CC BY-SA 4.0, via Wikimedia Commons.
Sources
- Governor Abbott Directs TCEQ To Halt Data Center Permits, Office of the Texas Governor
- Governor Abbott letter to TCEQ Executive Director Kelly Keel, Sept. 21, 2026
- TCEQ response to Gov. Abbott Sept. 21 directive on data centers, Oct. 19, 2026
- Governor Abbott letter to PUC and ERCOT on data center verification and community impact information, Aug. 3, 2026
- ERCOT letter and presentations, PUC Project No. 59142, Item 78, filed Nov. 4, 2026
- Data Center State and Community Impact RFI: Preliminary Summary, ERCOT presentation to the PUC, Nov. 5, 2026
- ERCOT Request for Information Regarding Data Center State and Community Impacts
- ERCOT updates on Batch Zero and Community Impact Review Process, PUC Project No. 59142, Item 52, Aug. 20, 2026
- PUCT Open Meetings and Agendas
- TCEQ Air Permitting
- TCEQ Stormwater General Permit for Construction Activities (TXR150000)